Building Hoover Dam: The Real Footage

Thousands of men turned the Colorado River, hung from ropes over Black Canyon and poured what was then the tallest dam in the world, finishing more than two years early. This is how Hoover Dam was built, and what it cost.

Giants on Film ·

A high scaler swings out on his rope over a slab on the wall of Black Canyon.

A river in the way

Watch this chapter · 0:00

Bureau of Reclamation engineers worked out that if Hoover Dam had been poured in one continuous block, its concrete would have taken 125 years to cool. It would still be cooling today. So it was built instead as separate columns, chilled from the inside with ice water, and when it was finished in 1935 it stood 726 feet, about 221 metres, from foundation rock to the roadway on its crest: the tallest dam in the world.

Before any of that concrete could go in, the men in Black Canyon had to move a river.

Left alone, the Colorado flooded in the spring and dried up in the summer. "Every spring they awaited with dread the coming of a flood," Franklin Roosevelt later said of the people of California's Imperial Valley. In 1905 the river broke through the diversion works near the Mexican border and poured north into the valley, filling a desert basin to make the Salton Sea.

On December 21, 1928, President Calvin Coolidge signed the Boulder Canyon Project Act. It called for a dam to control the floods, store water for farms and cities, and generate power. The site chosen was Black Canyon, on the Arizona-Nevada state line, about 50 kilometres from Las Vegas, then a town of about 5,000 people.

Black-and-white film frame of the Colorado River running between steep, sunlit rock walls in Black Canyon, a thin footbridge strung across the water
Archive The Colorado River in Black Canyon, in the Bureau of Reclamation's film. U.S. Bureau of Reclamation film, “Boulder Dam” (Prelinger Archives)

The men who came

Watch this chapter · 1:22

In the depths of the Depression, the government received only three bids. The lowest, $48,890,995.50, came from a group of western builders bidding together under one name: Six Companies. Their man on the ground was Frank Crowe, a veteran dam builder who had spent 20 years with Reclamation.

Thousands of unemployed men and their families poured into Las Vegas, hoping for work. Many camped on the floor of Black Canyon, near the construction site, in a settlement called Ragtown, made of tents, cardboard boxes and anything else families could find. In the summer of 1931 the canyon floor reached well over 120 degrees Fahrenheit, around 50 Celsius. In the new diversion tunnels it reached 140 Fahrenheit, 60 Celsius. By the end of that year, 16 people had died of heat prostration.

Pay ran from 50 cents to $1.25 an hour, for eight-hour days. On August 7, 1931, Six Companies moved a group of diversion-tunnel workers to lower-paying jobs. Tunnel crews walked out, and within days Six Companies had stopped all work and laid off the whole workforce. The strikers wanted clean water, flush toilets, ice water on the job, and for the company to obey the mining laws of Nevada and Arizona. Crowe rejected every demand. Afraid of losing their jobs, the strikers voted to go back.

The pay cut stood, but Six Companies pledged it would be the last, and work was sped up on housing in a new town for the workers: Boulder City. It had large dormitories for single men and cottages of one, two and three rooms for families. Gambling and drinking were banned, and Black workers were not allowed to live there.

A crowded mess hall full of men in work clothes eating at long tables under a steel roof, a waiter in a white jacket among them
Archive Workers fill the long tables of a mess hall, in the Bureau of Reclamation's film. U.S. Bureau of Reclamation film, “Boulder Dam” (Prelinger Archives)

Turning the river

Watch this chapter · 3:01

To move the Colorado, Six Companies drove four tunnels through the walls of Black Canyon, two on each side of the river, each bored 56 feet, 17 metres, across. Together they ran for nearly 16,000 feet, more than three miles.

At the rock face worked the drilling jumbos, trucks carrying platforms of drillers: backed up to the face, they put 24 to 30 drills to work at once. Once lights were installed, the work went on around the clock.

The trucks that hauled out the broken rock ran on gasoline, and their exhaust was trapped in the tunnels, building up carbon monoxide. Nevada law banned gas-powered vehicles underground, and in 1931 the state's inspector of mines told Six Companies to stop using them or face a lawsuit. Federal lawyers argued that state law did not apply to a federal project. The trucks kept running. When men fell very ill, or even died, after working in the tunnels, company doctors said it was a form of pneumonia.

The tunnels were finished in November 1932, almost a full year ahead of schedule. Then more than 100 trucks dumped rock and earth into the river, one load every 15 seconds, all through the night. Early on the morning of November 14, 1932, the whole Colorado turned and ran into the tunnels.

A truck standing under a tall scaffold of platforms and drills, at the rough rock face inside a tunnel
Archive A drilling jumbo, a truck carrying platforms for the drillers, at the rock face in a diversion tunnel. U.S. Bureau of Reclamation film, “Boulder Dam” (Prelinger Archives)
White water surging into the dark arched mouth of a concrete-lined tunnel at the foot of a cliff
Archive The Colorado pours into the mouth of a diversion tunnel. U.S. Bureau of Reclamation film, “Boulder Dam” (Prelinger Archives)

Cofferdams sealed the site off above and below. The upper one stood 98 feet high and was 750 feet thick at its base. Between them, in the dry riverbed, the men dug through thousands of years of accumulated silt to reach sound rock.

Men on ropes

Watch this chapter · 4:14

High above, millions of years of weather had worn at the canyon walls, and water freezing in the cracks had split the rock. All that loose rock had to come off before the dam could be built.

The men who did it were called high scalers. They climbed down the canyon walls on ropes and worked hanging over empty space. Jackhammers weighing 44 pounds, 20 kilograms, were lowered to them. They drilled the rock, loaded the holes with dynamite, and after the shot, broken stone sometimes had to be levered free with crowbars. Some had been sailors, some circus acrobats, and some were Native Americans. Reclamation calls it perhaps the most physically demanding work on the whole project.

Close view of a high scaler in a hard hat and work shirt gripping his rope as he hangs against a rough rock wall
Archive A high scaler in a hard hat hangs on his rope against the canyon wall. U.S. Bureau of Reclamation film, “Boulder Dam” (Prelinger Archives)

The danger from falling rocks and dropped tools was extreme, so the scalers made their own hard hats, coating cloth hats with coal tar. Several men were hit by falling rocks so hard that their jaws broke, yet their skulls were not fractured. Six Companies later issued commercially made hard hats to every man on the project.

One scaler, Louis "The Human Pendulum" Fagan, spent several weeks ferrying a crew around a jutting boulder on the Arizona side, twice a day, each man wrapping his legs around Fagan's waist.

On September 21, 1931, Jack Russell was stripping rock from the canyon wall. He fell 400 feet, about 120 metres, and died.

Other falls ended differently. Reclamation tells how Burl Rutledge, one of its engineers, slipped from the canyon rim. Twenty-five feet below, the high scaler Oliver Cowan heard him, swung out on his rope and caught him by the leg in mid-air. A few seconds later another scaler, Arnold Parks, swung over and pinned him to the wall, and they held him until a line could be dropped and tied around him. The shaken engineer was pulled to safety, unharmed.

Pouring the dam

Watch this chapter · 5:31

The first concrete went into the dam on June 6, 1933, and it came from above. Nine cableways spanned the canyon, lowering bottom-dump buckets of up to 8 cubic yards, about 6 cubic metres, to the men in the forms.

The dam rose as some 215 blocks in vertical columns, from about 60 feet square at the upstream face to about 25 feet square at the downstream face. No block could rise more than five feet, a metre and a half, in 72 hours. The reason was heat. Setting concrete gives off a tremendous amount, and poured as one mass, the dam would have cracked as it cooled.

Seen from above, a large round bucket marked 9 is lowered over wooden block forms on the canyon floor while a crew of men waits below
Archive A bucket of concrete comes down among the crew, in the film's sequence of the first pour. U.S. Bureau of Reclamation film, “Boulder Dam” (Prelinger Archives)
Looking down from the canyon rim onto a checkerboard of square concrete blocks in wooden forms, standing at different heights between the canyon walls
Archive The dam rising as separate blocks at different heights, seen from the canyon rim. U.S. Bureau of Reclamation film, “Boulder Dam” (Prelinger Archives)

So every block was laced with one-inch steel pipe. River water ran through it first, then ice water from a refrigeration plant at the lower cofferdam, with the cooling power of 1,000 tons of ice a day, about 900 tonnes. Altogether, more than 582 miles of pipe went into the concrete, over 930 kilometres. When a block had cooled, its pipes were filled with grout, and grout was forced into the joints between the blocks, bonding the dam into a single mass.

The last concrete went in on May 29, 1935: three and a quarter million cubic yards in the dam, about 2.5 million cubic metres. Reclamation says Hoover Dam was the first structure built by people to exceed the masonry mass of the Great Pyramid of Giza. With the power plant and the other works, there was enough concrete to pave a highway 16 feet wide, about five metres, from San Francisco to New York.

The tall, curved concrete face of the dam, marked by the joints between its blocks, with a scaffold tower and pipes running down it
Archive The curved downstream face of the dam rising, seen from the rim. U.S. Bureau of Reclamation film, “Boulder Dam” (Prelinger Archives)

Two years early

Watch this chapter · 6:50

On September 30, 1935, President Franklin Roosevelt came to dedicate the dam. "This morning I came, I saw and I was conquered," he said, "as everyone would be who sees for the first time this great feat of mankind."

In his speech he called it Boulder Dam. In 1930 the Secretary of the Interior, Ray Lyman Wilbur, had ordered that it be called Hoover Dam, but from 1933 the Roosevelt administration called it Boulder Dam, and the name Hoover Dam was not restored until 1947, in a resolution signed by President Harry Truman.

President Franklin Roosevelt in a dark suit and glasses speaking at a lectern with microphones, a crowd of men and women around him under a wooden roof
Archive President Franklin Roosevelt speaks at the dedication of the dam, September 30, 1935. U.S. Bureau of Reclamation film, “Boulder Dam” (Prelinger Archives)

The contract had allowed seven years from April 20, 1931. On March 1, 1936, more than two years early, the government formally accepted the dam. The dam's first generator went into full operation on October 26, 1936. For about ten years from 1939, its power plant was the largest hydroelectric plant in the world.

It is still working. In an average year the dam generates about 4 billion kilowatt-hours, enough to serve 1.3 million people in Nevada, Arizona and California. And Lake Mead can store the entire average flow of the Colorado for two years: the same river that once broke loose and filled the Salton Sea.

The price

Watch this chapter · 7:54

Officially, 96 men died building Hoover Dam. The count includes only men who died at the dam site, classed as industrial fatalities; it leaves out deaths from heat, pneumonia and heart trouble.

The project's own records list 213 deaths of every kind through 1935, on the job and off it. Forty-two of them were put down as pneumonia. Workers were certain the "pneumonia" was really caused by the fumes in the tunnels. It was never officially proven. In 1933, six tunnel workers sued Six Companies for carbon monoxide poisoning, each seeking $75,000 plus lost wages. The company hired a private detective to dig into their pasts, then settled out of court with 50 plaintiffs for an undisclosed sum. Reclamation's own learning packet says several dozen more died later, from heat or carbon monoxide poisoning suffered on the job.

The historian Dennis McBride puts it plainly: "There is no dependable number. There just isn't."

And despite the legend, no one is buried in the concrete. The concrete rose only slightly at any one time, and several men watched each placement, so Reclamation says it would have been virtually impossible for anyone to be buried in it.

But one story is true. J.G. Tierney, a Reclamation man on a survey crew working from barges on the Colorado to find the dam site, drowned in the river on December 20, years before construction began. His only son, Patrick, worked on the dam. On December 20, 1935, the same date, he fell to his death from one of the intake towers. He is often called the last man to die building Hoover Dam.

Two tall round towers of reinforcing steel and concrete rising in their forms beside the rock of the canyon wall, cables crossing in front
Archive Two intake towers rise in their forms beside the canyon wall. U.S. Bureau of Reclamation film, “Boulder Dam” (Prelinger Archives)

Near the dam, a bronze plaque remembers the 96 men who officially died. It begins with seven words: "They died to make the desert bloom."

Timeline

  1. 1905 The Colorado breaks through diversion works near the Mexican border and begins filling a desert basin, making the Salton Sea
  2. Dec. 21, 1928 President Calvin Coolidge signs the Boulder Canyon Project Act
  3. Aug. 7, 1931 Six Companies moves diversion-tunnel workers to lower-paying jobs; tunnel crews walk out, and within days the company shuts down the whole job
  4. Nov. 14, 1932 The whole Colorado is turned into the diversion tunnels
  5. June 6, 1933 The first concrete goes into the dam
  6. May 29, 1935 The last concrete goes into the dam
  7. Sept. 30, 1935 President Franklin Roosevelt dedicates the dam, calling it Boulder Dam
  8. Mar. 1, 1936 The government formally accepts the dam, more than two years ahead of the contract deadline

Shorts from this film

See it in the film

The stories of giant structures, machines and disasters, told through real archive film and 3D reconstructions. A new documentary every Monday.

Next stories

All documentaries →

Sources and credits

  1. Footage: Boulder Dam: The Pictorial Record of Man's Conquest of the Colorado River, Part I, silent version (U.S. Bureau of Reclamation; Prelinger Archives)
  2. Footage: Boulder Dam: The Pictorial Record of Man's Conquest of the Colorado River, Parts III and IV, silent version (U.S. Bureau of Reclamation; Prelinger Archives)
  3. Footage: Boulder Dam: The Pictorial Record of Man's Conquest of the Colorado River, complete sound version (U.S. Bureau of Reclamation; Prelinger Archives)
  4. Footage: The Story of Hoover Dam (U.S. Bureau of Reclamation; National Archives, ARC 37058)
  5. Bureau of Reclamation: The Story of Hoover Dam, Essays: Concrete
  6. Bureau of Reclamation: Hoover Dam, Frequently Asked Questions and Answers (the dam)
  7. Bureau of Reclamation: The Story of Hoover Dam, Essays: What Is Biggest?
  8. Bureau of Reclamation: The Story of Hoover Dam, Essays: Tunnels
  9. Bureau of Reclamation: Hoover Dam, project and facility data
  10. Bureau of Reclamation: Fatalities at Hoover Dam, 1931 and Earlier (from the Hoover Dam Project History)
  11. Bureau of Reclamation: The Story of Hoover Dam, Essays: Wages
  12. Bureau of Reclamation: The Story of Hoover Dam, Essays: Cofferdams
  13. Bureau of Reclamation: The Story of Hoover Dam, Essays: High Scalers
  14. Bureau of Reclamation: Hoover Dam Chronology
  15. Bureau of Reclamation: What's in a Name? (the naming of Hoover Dam)
  16. Bureau of Reclamation: Hoover Dam, Sound Bytes
  17. Bureau of Reclamation: Hoover Dam, Frequently Asked Questions: Hydropower at Hoover Dam
  18. Bureau of Reclamation: Lake Mead, Frequently Asked Questions and Answers
  19. Bureau of Reclamation: The Story of Hoover Dam, Essays: Fatalities at Hoover Dam
  20. Bureau of Reclamation: 1935 Fatalities and Summary of Fatalities (from the Hoover Dam Project History)
  21. Bureau of Reclamation: Hoover Dam Learning Packet (PDF)
  22. Bureau of Reclamation: The Story of Hoover Dam, Essays: Artwork
  23. National Archives: Milestone Documents, Boulder Canyon Project Act (1928)
  24. The American Presidency Project, UC Santa Barbara: Franklin D. Roosevelt, Address at the Dedication of Boulder Dam (September 30, 1935)
  25. Encyclopaedia Britannica: Salton Sea
  26. Library of Congress: Today in History, December 21: The Hoover Dam Story
  27. UNLV Special Collections and Archives, Hoover Dam collection: Ragtown
  28. UNLV Special Collections and Archives, Hoover Dam collection: How Much Were the Bids?
  29. UNLV Special Collections and Archives, Hoover Dam collection: Formation of Six Companies
  30. UNLV Special Collections and Archives, Hoover Dam collection: The Work Day
  31. UNLV Special Collections and Archives, Hoover Dam collection: Lawsuit against Six Companies
  32. UNLV Special Collections and Archives, Hoover Dam collection: The Dam Rises
  33. PBS / WGBH American Experience: Hoover Dam, The Workers' Strike
  34. PBS / WGBH American Experience: Hoover Dam, Building Boulder City
  35. Las Vegas Review-Journal (via Boulder City Review): Father, son die on same day 14 years apart working on Hoover Dam (Henry Brean, 2016)